Incheon Seoknam Innovative Logistics Center Fire Damage Restoration Project

  • Incheon Seoknam Innovative Logistics Center Fire Damage Restoration Project 1번 상세이미지 썸네일
  • Incheon Seoknam Innovative Logistics Center Fire Damage Restoration Project 2번 상세이미지 썸네일

Information

The Incheon Seoknam Innovative Logistics Center was successfully completed in August 2023. With a vast total floor area of approximately 290,000㎡ spanning one basement and eight above-ground floors, the project has drawn attention as a secure investment with confirmed pre-lease and pre-sale agreements.

BAUM CM was urgently brought in as the Project Manager (PM) just two months before completion and played a decisive role in steering the project to success. By swiftly and systematically resolving complex on-site issues between the previous CM firm and the contractor, BAUM CM ensured that the occupancy permit was obtained on schedule. Even after an unexpected fire incident post-completion, BAUM CM immediately established a comprehensive fire recovery plan and led the restoration process with precision and control. Through seamless coordination with both the master lessee and the buyer, the team successfully finalized the handover, confirming the facility’s stable and uninterrupted operation.

This project allowed BAUM CM to build specialized expertise and technical know-how in fire recovery management for large-scale logistics facilities.

Key capabilities established through this experience include:
- Rapid damage assessment: Accurate analysis of fire extent and impact to devise optimal recovery strategies
- Material and Technique Optimization: Practical know-how in choosing and implementing the best restoration techniques and materials according to specific damage conditions
- Coordination with insurers and authorities: Proficient management of insurance claims, safety inspections, and regulatory approvals
- Risk minimization: Achieving quality standards that meet both tenant and buyer requirements
- Schedule Optimization: Systematic process management ensuring complete recovery within a limited timeframe while maintaining quality and safety standards

Through its professionalism and accountable project management, BAUM CM has positioned the Incheon Seoknam Innovative Logistics Center as a benchmark for large-scale logistics infrastructure development — while simultaneously establishing itself as a leader in fire recovery project management.

Project Fact

  • Project

    Incheon Seoknam Innovative Logistics Center Fire Damage Restoration Project

  • Region

    Seoknam-dong, Seo-gu Incheon

  • GFA

    299,308㎡

  • Purpose

    Logistics Center

  • Orderer

    KKR

  • Service

    Constuction Management

  • Period

    2023.06 ~ 2024.04

  • Scale

    B1F, 8F